I-95 (PGA Boulevard to Donald Ross Road)

Description
This project includes continuing the HOV lane, widening 2.9 miles of existing interstate to 10 lanes (five in each direction), and installing new signs, signalization, lighting and landscaping.


Start Date
September 14, 2008

Completion
Winter 2011

Project Length
4.3 miles

Cost
$44 million

Project Team

FDOT Construction Project Manager
Scott Burrie

CCEI Senior Project Engineer
Michael Irwin, P.E., TBE Group

Contractor
Community Asphalt Corporation

Public Information Officer
Alicia De Fago
561-718-4709
95info@pbfdot.com